Pinellas mosque rebuild near Tarpon Springs faces legal challenges and a $100,000 lien after 4-3 vote

The Florida Press Newsroom6 min read
Pinellas mosque rebuild near Tarpon Springs faces legal challenges and a $100,000 lien after 4-3 vote
Photo via Yahoo News

A plan to tear down and replace Masjid Al-Rahman, a mosque on Keystone Road in unincorporated Pinellas County near Tarpon Springs, has cleared every land-use vote it needs, but it now faces two legal challenges and an unpaid code-enforcement lien of more than $100,000 that could hold up permits. The Pinellas County Commission approved the final countywide land-use change on a 4-3 vote on Oct. 13. Unanimous advisory votes earlier in the year have since given way to heated public meetings.

The dispute has drawn questions about how the county described the project in its paperwork, whether neighbors were properly notified and how the county has handled a lien tied to code violations that date back to 2016, according to county records and reporting by the St. Pete Catalyst published by WUSF.

What the mosque wants to build

The property owner, Al Rahman Inc., owns about 2.69 acres at 2577 Keystone Road in East Lake Tarpon, near East Lake Drive. It wants to demolish the existing building and replace it with a slightly larger one, expand parking, improve stormwater drainage and close the driveway on Keystone Road so that all traffic uses East Lake Drive instead.

To do that, the owner asked the county to change the property's future land use from Residential Rural to Institutional and its zoning from Residential Agriculture to Limited Institutional with a conditional overlay. Minutes from the county's Local Planning Agency hearing on May 13 list the limits written into that overlay:

  • Uses restricted to a community assembly facility with accessory storage
  • Maximum floor area ratio of 0.3 and impervious surface ratio of 0.6
  • Minimum building setbacks of 50 feet on the front, sides and rear
  • Vehicle access only from East Lake Drive
  • Maximum building height of 35 feet
  • A five-foot landscape buffer on East Lake Drive and a 10-foot buffer on Keystone Road, which is a designated scenic noncommercial corridor

At that hearing, a representative for the applicant, Diogo Rodrigues, said the owner intends to bring the property up to current codes and build a new building of approximately the same size. County planning staff found the request consistent with the Pinellas County Comprehensive Plan and recommended approval. No one spoke for or against it, and the minutes note that no correspondence had been received.

How the approvals stacked up

The project passed through several boards before reaching the final countywide vote, with opposition building only near the end.

BoardActionVote
Local Planning Agency, May 13Recommended land-use and zoning changesUnanimous, 6-0
County Commission, June 16Approved local land-use and zoning changesApproved
Planners Advisory CommitteeRecommended countywide amendment17-0
Forward PinellasRecommended countywide amendment13-0
County Commission, Oct. 13Approved countywide land-use amendment4-3

The conditions attached at the end include the 35-foot height limit, 50-foot setbacks, additional landscaping and East Lake Drive access only, according to the WUSF report.

The 'community assembly' label

Commissioner Vince Nowicki questioned why county staff reports described the project as a "community assembly" facility without saying it was a mosque. Staff acknowledged that the descriptive language had been left out, and Nowicki said he did not know whether that omission was deliberate, the Catalyst reported.

Older county records describe the use more plainly. When the county's Board of Adjustment and Appeals considered an earlier expansion request from Al Rahman Inc. in September 2021, the case was described as a meeting hall and community assembly facility, identified in the record as a place of worship. At that time, staff noted that neighboring land to the west was already used for institutional purposes, including a place of worship and an assisted living facility, and said the mosque property would eventually have to be redesignated Institutional to meet the county's acreage rules.

Nowicki has said his focus is the county's procedures rather than the religious objections some residents have raised. "I can only focus on the process, the policy, the procedure," he said, according to the Catalyst.

An unpaid lien from 2016

The more concrete obstacle may be money. A code-enforcement lien tied to violations from 2016 remains unpaid. The 2021 Board of Adjustment minutes show that a speaker identified as Roy Thomas of Tarpon Springs raised the property's code violations at that hearing, and county staff said the owner had not brought the property into compliance and daily fines were accruing. A county attorney said then that no development permits or approvals should be issued until code violations are addressed, and the board's chairman said that approval was conditioned on violations being corrected, fines paid and liens removed.

The property was brought into compliance on Oct. 25, 2023. The lien was reduced in 2021, when the commission adopted a lien settlement program that capped liens at $20,000 per violation for single-family homes and $100,000 per violation for other properties. Even so, the balance stands at $100,353.23 including costs. The owner may apply to reduce it to $40,779.49 plus $353.23 in costs.

Under Section 134-8(f) of the county's Land Development Code, the county cannot process site plans or building permits until the lien is paid, though there are exceptions for certain corrective work and health and safety issues. Nowicki has said he plans to review how the county has handled liens on other properties.

Two legal challenges

Thomas, an adjoining property owner, has filed a petition in the Sixth Judicial Circuit Court, dated Nov. 12, challenging the decision over public notice, traffic and code obligations he says were not addressed. A separate petition from a group called Pinellas County Watchdogs and two of its members asks for an administrative hearing through Florida's Division of Administrative Hearings. The Catalyst said it could not independently confirm the status of either case.

The county maintains that notice was proper. It says notices went to property owners within 300 feet before the May hearing and a sign was posted on the property April 16, and the County Attorney's Office concluded that notification met legal requirements.

Heated meetings

Public comment on the project continued at commission meetings on Oct. 27 and Nov. 17, after the final vote, with some speakers raising objections based on religion and others describing the mosque's members as good neighbors. During the October meeting, a woman wearing a burqa played a recording of the Islamic call to prayer at the podium instead of speaking. Commission Chairman Dave Eggers told her county rules require spoken comments, and a Pinellas County Sheriff's Office deputy escorted her out. The sheriff's office said she left without further incident and would not face charges.

What's next

With the land-use and zoning changes in place, the next step for Al Rahman Inc. is site plan review, the stage at which drainage, parking and access plans are checked against county code. That review cannot move forward until the lien is settled, and the owner had not submitted new documents as of Nov. 13. Representatives of Masjid Al-Rahman did not respond to the Catalyst's request for comment.

The outcome of Thomas' court petition and the administrative hearing request could also affect the timeline.

Spotted an issue with this article?

Have something to say about this story?

Write us a letter

Comments

Commenting is temporarily unavailable.

No comments yet. Be the first to weigh in.

Related Coverage