Project Tango Lawyer Threatened to Sue Palm Beach County and Its Zoning Director Days Before Staff Approved a Data Center Expansion

The Florida Press Newsroom7 min read
Project Tango Lawyer Threatened to Sue Palm Beach County and Its Zoning Director Days Before Staff Approved a Data Center Expansion
Photo via WPTV News Channel 5 West Palm

Ten days before Palm Beach County's zoning staff quietly approved a major expansion of the Project Tango data center campus, a lawyer for the developer sent the county a 180-page letter warning of "significant and potentially catastrophic financial liability" and threatening to sue both the county and its zoning director personally, according to reporting by WLRN and WPTV published this week.

The Oct. 7 administrative approval more than tripled the data center space allowed on the 202-acre site west of the Arden community, from 200,000 to 700,000 square feet, without a public hearing or a vote of the County Commission. That approval came less than three months after commissioners voted 5-1 to reject a far larger version of the project, and the letter's disclosure has prompted the area's new commissioner to call for the decision to be overturned.

What the letter said

The letter, dated Sept. 28, was written by Ethan Loeb, a Tampa attorney representing PBA Holdings, the property owner and applicant formerly known as Palm Beach Aggregates, according to WLRN, which first reported it in a story by Joel Engelhardt of Stet News. It warned that the county faced "significant and potentially catastrophic financial liability" if it departed from its own zoning rules, and it threatened lawsuits against the county and against Zoning Director Wendy Hernandez, who serves as the development review officer, along with other staff.

WPTV reported that the letter said damages to PBA Holdings could be too large for the county to pay. Loeb said the company would sue under the Bert J. Harris Jr. Private Property Rights Protection Act, the Florida law that lets landowners seek compensation when government action unfairly burdens their property. PBA has estimated that the property, built out with a larger data center and more warehouses, would be worth $34 billion, according to WLRN.

The letter also challenged conditions staff wanted to attach to the project. Loeb called one staff comment "nonsensical" and suggested a "shift in the apparent political winds" might explain why staff had changed position, WLRN reported. WPTV reported that the letter objected to requirements for continuous sound studies and real-time public noise monitoring, arguing the county had never imposed such conditions on another property owner.

The Oct. 7 approval

Hernandez signed the administrative approval on Oct. 7, ten days after the letter was dated. Staff still attached conditions that PBA Holdings found objectionable, WLRN reported, including limits on megawatt capacity, a decommissioning plan, a check for foreign ownership and an 850-foot building setback that Loeb argued does not appear in the zoning code. Staff had also sought studies of noise, vibration and heat, which the company opposed.

The approval drew scrutiny at a County Commission meeting last week, when commissioners questioned staff about how the data center space could grow without their involvement. No one raised the letter during that discussion, according to WLRN.

Commissioners split on the issue. Katherine Waldron, the newly elected District 6 commissioner who represents the area, along with Marci Woodward and Maria Sachs, criticized the decision and said the public had been shut out. Joel Flores, Maria Marino and Bobby Powell argued staff had to follow existing rules and past commission decisions. Erica Whitfield did not take a position. County Administrator Joe Abruzzo backed his staff and said the applicant was "working the system," WLRN reported.

After learning of the letter, Waldron called it a personal threat against a county employee. She told WPTV the threat "corrupts the process" and said the approval should be considered for overturning.

How Project Tango got here

Project Tango sits on Southern Boulevard near the 20-Mile Bend, within the previously approved Central Park Commerce Center, bordering Arden in the Loxahatchee area of western Palm Beach County. A 2016 county approval allowed 1.2 million square feet of warehouses and a data center of about 206,000 square feet on the site, and a 2016 county ruling classified data centers as a light industrial use. PBA Holdings argues the county encouraged the project based on that ruling.

The county approved 64 additional acres without controversy in January 2024. Opposition grew in December 2025, when the hyperscale nature of the project became clear. The developer's request that went before commissioners this summer called for nearly 3.6 million square feet on 202 acres, including warehouses, an artificial intelligence data center and utility structures, with a power demand of 600 megawatts. That is 12 times the 50-megawatt threshold that triggers stricter review under Florida law, according to WLRN.

The key dates so far:

DateEvent
Jan. 2024County approves 64 added acres
Dec. 2025Hyperscale plan becomes clear; opposition grows
July 2, 2026Zoning Commission recommends denial, 6-0
July 15, 2026County Commission rejects expansion, 5-1
Sept. 28, 2026Loeb letter to county
Oct. 7, 2026Staff approves 700,000 square feet of data center space
Oct. 9, 2026PBA Holdings sues over choice of magistrate

At the July 15 hearing, Marino cast the only vote in favor. District 6 Commissioner Sara Baxter, the county mayor at the time of the hearing, recused herself after publicly opposing the project. Woodward said the plan was not compatible with the county's comprehensive plan and needed too many conditions to fit. The developer had already cut the data center portion by more than 40% before the vote, but the reductions did not win over the board.

What residents fear

Arden residents have voiced what WLRN called "unrelenting opposition" since December 2025, citing the project's power and water use, noise and other effects on the neighborhood. Saddle View Elementary School sits roughly 900 to 1,200 feet from the site, which is why staff proposed the 850-foot setback.

During the summer hearings, the developer said its closed-loop cooling system would use 100,000 gallons of potable water a day. An independent noise reviewer for the county, Santiago Lattanzio, disputed the developer's sound modeling, saying it accounted for only five fans and five chillers.

Janice Ridenour, an Arden resident who helped lead opposition to the larger expansion, told WPTV the letter was shocking and that the October approval made it seem the residents' work leading up to the July vote had accomplished nothing. Ridenour and Waldron both worry that the approval could set a path for other warehouse properties zoned light industrial to be turned into data centers without a commission vote.

That concern is not hypothetical. A second applicant, WPB Logistics, backed by TPA Group of Atlanta, has proposed converting 1.2 million square feet of warehouse space into 1.1 million square feet of data center space, WLRN reported. Arden attorney John Eubanks argued that application came after the county's July 7 zoning in progress notice, while county officials say it was first filed June 16 and resubmitted July 14 after a missing document. Eubanks has also argued that a PBA Holdings extension request was improper, making its application "null and void."

A county moratorium and a statewide rush

The fight over Project Tango drove Palm Beach County to pause new large data center applications. Commissioners voted 7-0 on Aug. 27 to advance a one-year moratorium on facilities expected to draw 50 megawatts or more at peak demand, measured across an entire site so projects cannot be split to dodge the rule, and the moratorium was enacted in September. At that August hearing Sachs complained that the county had not known who owns Project Tango. "Who owns these hyperscale data centers? We did not know that for Project Tango," she said. The end user of the campus still has not been publicly identified.

Palm Beach County is not alone. The Florida Press reported this month on a proposed Auburndale data center that could draw 700 megawatts and on Hillsborough County delaying its own moratorium vote. In Washington, Florida Sens. Rick Scott and Ashley Moody voted for a Senate permitting bill aimed at data center costs as Florida braces for a surge in power demand from artificial intelligence.

What's next

PBA Holdings sued the county on Oct. 9 under the Florida Land Use and Environmental Dispute Resolution Act after the two sides could not agree on a special magistrate, WLRN reported. That suit ended last week once they agreed on retired Palm Beach Circuit Judge James Martz. The sides are aiming for a public hearing on Dec. 7. The question before Martz is whether PBA can expand the overall project from 2.02 million to 3.6 million square feet. His recommendation is not binding: the County Commission can accept or reject it, and PBA could sue if it disagrees.

Commissioners also agreed last week to form a seven-member technical advisory committee and to hire the firm Vanasse Hangen Brustlin Inc., known as VHB, for up to $225,000 under emergency rules. Chief Deputy County Administrator Patrick Rutter told the board: "Time is of the essence."

WPTV said it contacted the Project Tango developers about the October expansion and did not receive a response.

Spotted an issue with this article?

Have something to say about this story?

Write us a letter

Comments

Commenting is temporarily unavailable.

No comments yet. Be the first to weigh in.

Related Coverage