NASA targets summer 2027 for Artemis III, a 14-day Earth-orbit test of Blue Origin and SpaceX landers from Kennedy

The Florida Press Newsroom5 min read
NASA leaders to update Artemis acceleration and 2028 Moon landing plan at Kennedy on Oct. 23
Photo via NASA

NASA is aiming to launch Artemis III from Kennedy Space Center as early as summer 2027 on a 14-day flight in Earth orbit that will test lunar landers from both Blue Origin and SpaceX, agency leaders said at a news conference at the Florida spaceport on Friday, Oct. 23. The mission keeps the agency on a path toward two crewed Moon landings in 2028, and it will put three heavy-lift launches into a tight window, at least two of them from Florida's Space Coast.

The update came from NASA Administrator Jared Isaacman, Associate Administrator Amit Kshatriya and Artemis program manager Jeremy Parsons, who briefed reporters at Kennedy at 2 p.m. Friday, according to a NASA media advisory. Officials did not commit to an exact launch month, and they did not spell out how the agency would make up time lost to recent setbacks, FOX 35 Orlando reported.

What NASA announced at Kennedy

Artemis III was reworked earlier this year from a lunar landing into a test flight close to home. Four astronauts will fly the Orion spacecraft into low Earth orbit: NASA's Randy Bresnik as commander, European Space Agency astronaut Luca Parmitano as pilot, and NASA's Andre Douglas and Frank Rubio as mission specialists. Their job is to practice the rendezvous, docking, habitation and operating procedures that crews will need when landings begin near the Moon's South Pole in 2028, according to a NASA mission overview published after the briefing.

Parsons described the scale of the test in NASA's overview, saying that every piece of the mission in Earth orbit "is designed to reduce risk before we put astronauts back on the Moon." He added that NASA is "launching three spacecraft on three different rockets," something the agency has never attempted.

Isaacman framed the plan as part of a broader push to speed the program up. In a separate NASA release on the landers, he said the agency's "machine shops are running 24/7" and that its experts are "in the field attacking the critical path." At the briefing, he said that confronting the agency's shortcomings and acting on them "is how confidence is earned," according to FOX 35.

The 14-day flight plan, step by step

NASA laid out the order of events in its mission overview. The sequence depends on two commercial launches bracketing the agency's own Space Launch System rocket.

PhaseWhat happens
Blue Origin launchBlue Moon Mark 2 test article enters a circular orbit about 273 miles up; it can wait up to 30 days
SLS launch from KennedyOrion and crew lift off days later, once Blue Moon is confirmed healthy
Flight days 1 and 2Crew checks out Orion and maneuvers toward the waiting lander
First dockingAbout two days docked with Blue Moon; crew opens the hatch and evaluates the cabin and life support
SpaceX launch from FloridaStarship Version 3 test article launches later in the mission, about six days after Orion, per FOX 35
Second dockingOrion docks with Starship for up to two hours; crew does not enter Starship
Final daysUp to five more days of suit, sensor, science and human-factors tests
ReturnSplashdown in the Pacific Ocean off California, with NASA and Navy recovery

Orion will first enter an elliptical orbit of 18 by 1,122 miles, then raise itself to a roughly circular orbit near 345 miles before closing in on Blue Moon, NASA said. Starship will fly lower, at 206 nautical miles, with an added docking system on its nose. The two dockings use different geometries: Orion connects to a port beside Blue Moon's crew cabin, then lines up nose to nose with Starship.

The crew will also fly a cellular biology experiment, test concepts for handling returned lunar samples, carry plant seeds and run a study of how astronauts could perform health checks without direct contact with mission control, according to NASA.

Where the two landers stand

NASA also announced changes to how both companies' landers will reach the Moon for the 2028 missions. The landers and Orion will no longer meet in the near-rectilinear halo orbit around the Moon that earlier plans called for. Instead, each provider will use an orbit suited to its own vehicle, according to the NASA release on lander development.

  • SpaceX Starship: The company will still refuel its lander in low Earth orbit using a series of tanker Starships that fill a depot ship. Under the revised plan, the Starship lander, launched from Florida, will wait in Earth orbit, dock with Orion and then fire its engines to push the combined stack to low lunar orbit. NASA said it is modifying Orion so Starship can do that. SpaceX added two demonstrations of its crew cabin, called Cabin 1, to its milestones.
  • Blue Origin Blue Moon: For its accelerated 2028 landing, Blue Origin will put off in-space propellant transfer and instead use three transfer stages, working like a multistage rocket, to send its Blue Moon Mark 2 Alpha lander to an elliptical polar orbit around the Moon. The company added human-in-the-loop testing and hardware readiness milestones.

Both companies must fly an uncrewed demonstration of their crewed landers before carrying astronauts. Under contract changes made earlier this year, neither provider is assigned to a specific landing. NASA will decide which company flies first in 2028 based on lander readiness, and a second crewed landing opportunity will follow, the agency said. NASA is planning two moonwalks of about two hours each on the first surface missions, using spacesuits from Axiom Space.

Catching up on a slipping schedule

The briefing followed a rough stretch for the schedule. In late September, FOX 35 reported on an internal workforce memo, first published by NASA Watch, in which Isaacman wrote that the agency was "~90 days broken against the Artemis III schedule." The same memo described a summer 2027 launch as the best-case scenario, one that would preserve up to two landing attempts in 2028.

Inside the Vehicle Assembly Building, the SLS solid rocket boosters for Artemis III are stacked, FOX 35 reported. NASA engineers recently resolved hydrogen leak problems after bringing the repair work in-house, according to the station, and managers are now directing employees to take hands-on roles on technical problems instead of waiting for outside contractors. Parsons said at the briefing that NASA is "strengthening the spaceflight workforce" and "rebuilding key competencies."

What it means for Kennedy and the Space Coast workforce

For Brevard County, Artemis III means at least two high-profile launches within days of each other: the crewed SLS and Orion from Kennedy, and a Starship test vehicle launched from Florida later in the mission, according to NASA. The 2028 landing plan also depends on a run of Starship tanker flights before the lander itself departs from Florida.

The agency's shift toward doing more work with its own civil servants is also reshaping jobs at the spaceport. A Florida WARN notice filed Oct. 16 shows Aetos Systems expects to lay off up to 126 employees working at Kennedy, News 6 ClickOrlando reported this week. Aetos is a subcontractor to Leidos on NASA's AEGIS contract, a 10-year, $2.5 billion award from 2021 for unified cloud, network and cybersecurity services, and the notice says that work will now be handled in-house by NASA. Some or all of the affected employees could receive offers to join NASA directly, and those who decline will be let go by Dec. 31, 2026, according to the notice as reported by the station.

That notice followed a separate one in late September, when Amentum reported it would eliminate 70 positions tied to its Base Operations and Spaceport Services work at Kennedy as NASA took that work in-house, according to local reports. Together, the two notices put close to 200 contractor jobs at the spaceport in flux before the end of the year, even as NASA says it is hiring the core talent it needs.

What's next

NASA has not named a launch month for Artemis III. Before it flies, Blue Origin and SpaceX must have their test articles ready to launch within days of the SLS, and the agency must hold its own schedule in the Vehicle Assembly Building. If the Earth-orbit test succeeds, NASA plans two Moon missions in 2028, with the first crewed landing since Apollo 17 in 1972 going to whichever lander is ready first. For Space Coast workers, the more immediate dates are the Dec. 31 deadline for Aetos employees and the agency's continuing push to move contractor work to civil servants.

Spotted an issue with this article?

Have something to say about this story?

Write us a letter

Comments

Commenting is temporarily unavailable.

No comments yet. Be the first to weigh in.

Related Coverage